How do I obtain a Rezoning Permit?
Call or visit the Planning Department to obtain a permit application.
Complete the application, including all pertinent data, and return it
to the Planning Department during counter hours.
The City will notify the applicant within 30 days if additional information
is required to process the application.
Once the application is deemed complete the appropriate hearings will
be scheduled. For Use Permit, Design Review, and Variance Permits, one
hearing before the Planning Commission is required. Once the Planning
Commission approves the application, there is a 10 day appeal period
in which the application could be appealed to the City Council. If appeal
in not submitted, then the application is deemed approved. For Land
Division or Rezoning Permits, hearings before the Planning Commission
and the City Council are required.